The iconic McPolin Barn is undergoing a structural upgrade.
Project Goal:
Bring the building up to current structural building code to protect it from seismic, wind, and snow loads.
Scope of Work:
-
Replace interior cable system (installed in 1992) with code-compliant internal steel-brace frame, shear walls, and footing system.
-
Restore original windows.
Anticipated Construction Start Date:
July 11, 2016
Construction Completion Date (Estimated):
November 1, 2016
Restricted Areas:
The barn, silos, and plaza at the shed will be fenced off.
On-Site Public Access:
The underpass, the driveway, and trail that splits from the driveway to the north behind the shed/reception building will remain open to the farm trail for public trail access.
Parking Restrictions:
Some spaces at the trailhead parking lot on the east side of SR224 will be reserved for construction personnel.
Public Restrooms:
Public restrooms at the site will remain open via the stairs to the west of the building.
Questions:
Matthew Twombly, Senior Project Manager
435.615.5177
mtwombly@parkcity.org