Main Street Water Line Project Begins April 1

Post Date:03/27/2024

Main Street Water Line Replacement Project, Phase I, to Begin April 1, 2024

In order to replace aging infrastructure and assure safe and reliable drinking water delivery to the heart of Park City, a three-phase project will launch April 1, 2024, to replace the water main, fire lines and water services in Main Street. The first system-wide upgrade since 1984, this work is necessary to prevent further pipe breaks and other system failures that are more common in aging infrastructure.

Working with the Historic Park City Alliance (HPCA), the City chose construction timelines that minimize impacts to area businesses and other stakeholders. This project is planned to be completed in the following three shoulder-seasons, which historically reflect the quietest business months on Main Street:

  • April 1-July 1, 2024: Phase I – Heber Avenue to 5th Street
  • April 1-July 1, 2025: Phase II– 5th Street to 3rd Street
  • April 1-July 1, 2026: Phase III – 3rd Street to Swede Alley

Phase I of this project will take place along Main Street from Heber Avenue to 5th Street, time permitting.